Progress payment stages, state by state

What your builder may claim, and when. One state caps it stage by stage, one publishes a template, and one says the payments must follow the work.

Checked 11 November 2026 against the sources linked under each section. Building law changes; check the source before you rely on a figure.

Victoria: capped stage by stage

Victoria is the state whose law sets the progress payment stages and caps each one. Under a major domestic building contract to build all stages of a home, a builder may claim no more than 5% deposit, 10% at base, 15% at frame, 35% at lock-up and 25% at fixing, leaving 10% for completion. The percentages are shares of the contract price, and each can only be claimed once that stage is finished.

Victoria: the statutory maximums
StageClaimPaid by then
Deposit5%5%
Base10%15%
Frame15%30%
Lock-up35%65%
Fixing25%90%
Completion10%100%

The deposit is capped too: 10% if the contract price is under $20,000, and 5% if it is $20,000 or more. On a $480,000 contract that is at most $24,000.

Domestic Building Contracts Act 1995 (Vic), section 40 (stages) and section 11 (deposit). Source: Consumer Affairs Victoria, “Deposits and payments for domestic building” (page updated 9 July 2025). Checked 11 November 2026.

A change has been announced and is not reflected here. The Domestic Building Contracts Amendment Act 2025 is reported to move the deposit cap and the stage table into regulations, with draft regulations proposing a higher deposit, a new site-preparation stage and a smaller lock-up claim. We have not been able to check the text of those regulations or a confirmed start date against a primary source, so the figures above are the ones in force as Consumer Affairs Victoria states them. This page is due to be re-checked by 1 December 2026.

Queensland: a template, and a rule

Queensland does not set stage percentages in law. It requires that each progress claim is proportionate to the work actually done on site. The Queensland Building and Construction Commission’s own template new-home contract prints this split as its first option: 5% deposit, 15% at base, 20% at frame, 25% at enclosed and 20% at fixing, leaving 15% for practical completion.

Queensland: the QBCC new home contract
StageClaimPaid by then
Deposit5%5%
Base15%20%
Frame20%40%
Enclosed25%65%
Fixing20%85%
Practical completion15%100%

The template itself warns the builder that the payments must be proportionate to the work, and to use its other option where these percentages would run ahead of it. Source: Queensland Building and Construction Commission, New Home Construction Contract template (July 2023). Checked 11 November 2026.

The deposit is capped by contract price: 20% on work up to $3,300, 10% from $3,301 to $19,999, and 5% from $20,000. A larger deposit is allowed where most of the work, by value, is made off site. Source: QBCC, “Understanding deposits and progress payments” (published 29 September 2025). Checked 11 November 2026.

New South Wales: payments follow the work

No set percentages. Progress payments must be authorised by the contract and either tied to a stage being finished or to work already done (section 8A), and every contract over $20,000 must carry a progress payment schedule. The deposit may not be more than 10% of the contract price, which on $480,000 is $48,000.

Home Building Act 1989 (NSW), section 8. Source: NSW Government, “Contracts for residential building work” (page updated 29 April 2026). Checked 11 November 2026.

The other states and territories

Not covered yet. We have not checked Western Australia, South Australia, Tasmania, the ACT or the Northern Territory against their own sources, so this page does not give figures for them. Your contract and your state’s building regulator are the place to look.

What the split does to your interest

The shares decide how fast the loan is drawn, and so how much interest you pay before the house is finished. On $480,000 at 6.6% over 9 months, stages evenly spaced, Victoria’s limits cost $9,742 in interest during the build and the Queensland template $10,217. A split with more of the money paid at base and frame — the one the design for this site was first drawn with, for example — would cost $11,167, $1,426 more than Victoria’s, and would be over the Victorian caps at both of those stages.

The progress payment calculator has both schedules built in, and a custom option for your own contract’s figures.

Questions for your builder

  • Which stages does the contract use, and what share of the price is due at each?
  • In Victoria: does the schedule differ from the statutory one, and if so, how was that agreed?
  • When is each stage expected, in weeks from the deposit?
  • What exactly has to be finished before each claim, in the contract’s own definitions?