Building? Your interest climbs stage by stage.
A construction loan pays your builder in stages. You only pay interest on what’s been drawn. Here’s what that looks like on your contract.
| Stage | Paid to builder | Drawn so far | Interest / month |
|---|---|---|---|
| Deposit 5% | $24,000 | $132 | |
| Base 10% | $48,000 | $396 | |
| Frame 15% | $72,000 | $792 | |
| Lock-up 35% | $168,000 | $1,716 | |
| Fixing 25% | $120,000 | $2,376 | |
| Completion 10% | $48,000 | $2,640 |
Victoria’s statutory stage limits (of the three states we have checked, the one that sets them in law), stages spaced evenly, interest only during the build, the whole contract borrowed, then 30 years of principal and interest. Your contract sets the real percentages and dates: change them on the full calculator.
Drawn in stages, not on day one
The same loan drawn in full on the first day would cost $23,760 in interest over 9 months, against $9,742 drawn in stages. That gap is the whole reason a construction loan exists.
The split is the law’s, not ours
In Victoria a builder may claim at most 5% deposit, 10% at base, 15% at frame, 35% at lock-up and 25% at fixing, leaving 10% for completion. Queensland’s template contract front-loads more, which on the same example costs $10,217. Stages by state
Your own money usually goes first
Lenders generally want your contribution spent before their money is drawn. Put $100,000 in first and the interest above falls to $5,821. Try it with your figures