Home / Guides / What the loan does not cover
What a construction loan does not cover
The loan is drawn against the contract. Anything that is not in the contract is yours to pay.
A construction loan is drawn in progress payments against your building contract. A cost that is not in the contract is not one of those payments, so it generally has to come from your own money, or be approved by the lender separately. On a new house that list is longer than most people expect.
The usual list
Check your own contract line by line, because builders differ. These are the items most often outside a house contract:
- Site costs the builder has excluded or quoted as provisional: excavation beyond an allowance, rock, retaining walls, extra piers.
- Driveways, paths and paving, and the crossover to the street.
- Fencing and gates.
- Landscaping, turf and garden beds, and any that the council requires.
- Window coverings: blinds, curtains and their tracks.
- Floor coverings in rooms the contract leaves unfinished.
- Letterbox, clothesline, TV antenna and similar finishing items.
- Connections to power, water, sewer, gas and the internet, where the contract stops at the boundary.
- On a knockdown rebuild: demolition, asbestos removal, tree removal and service disconnections, if they are not in the price. The knockdown rebuild page has a field for demolition.
Allowances move
Many contracts carry allowances for items that cannot be priced exactly yet, such as excavation or a kitchen benchtop. If the real cost comes in higher, the difference is added to the price. Whether the lender will fund the increase is the lender’s decision, and may need a new approval.
Variations are yours until proven otherwise
Anything you ask the builder to change after signing is a variation to the contract. The loan was approved against the original contract, so a variation may need the lender’s approval before it can be included in a progress payment, or it may simply be yours to pay. Ask before you sign the variation, not after.
The arithmetic
Add up what your contract leaves out and treat it as cash you need on top of your contribution, at the end of the build, when most of it falls due. The loan’s figures on this site — the interest during the build, stage by stage — are for the contract only, and say so.
Questions for your builder
- What is excluded from the price, in writing?
- Which items are allowances, and what are they based on?
- Where exactly do the service connections stop?
Questions for a broker or lender
- Will you fund items outside the contract, and how?
- Do variations need your approval before they can be claimed in a progress payment?